Cat.No. |
Categories and scope |
|---|---|
|
|
|
|
1 |
Request for Information (RFI) |
|
Delays in clarification on drawings from consultants / RFI sent to consultants |
|
|
2 |
Request for Drawings & related approvals (RFD) |
|
Request for Missing GFCs |
|
|
Delays in approval of shop drawings by consultants |
|
|
3 |
Request for Commercial Approval (RFC) |
|
Variation order / R&R |
|
|
Request for sanction of additional Preliminaries |
|
|
Request of additional cost entitlement |
|
|
Issues in the interpretation of contractual clauses / Contract amendments |
|
|
Issues regarding Contractors General Attendance for NSCs |
|
|
4 |
Request for Materials (RFM) |
|
RMC & Rebar procurement – PO approval / Phoenix procurement |
|
|
Rate approval for RM (basic rate items) |
|
|
5 |
Request for NSC management (RFN) |
|
Issue / Award of NSC tender |
|
|
Issue of NSC contract |
|
|
Amendment in NSC contract |
|
|
Contract administration / Contractual issues of NSC |
|
|
Approval/disapproval of NSC vendors |
|
|
NSC payment/ Running bills / Bills approval |
|
|
6 |
Request for Schedule amendment (RFS) |
|
Approval of Master schedule – cost & resources loaded |
|
|
Amendment to the Schedule |
|
|
7 |
Request for Technical & Administrative approval (RFT) |
|
Method statement/changes in Method statement |
|
|
Safety / quality / site cleanliness related issues |
|
|
Site logistics-related issues |
|
|
Changes in process/systems |
|
|
Changes in key resources |
|
|
Government approval related challenges. |
|
|
Availability of work front |
|
|
Construction power |
|
|
8 |
Request for Billing support (RFB) |
|
Delays and issues in Running Bills |
|
|
Deductions, recoveries etc. |
|
|
Mobilisation advance payment |
|
|
Contractors account reconciliation |
|
|
Contractors payments |
|
|
9 |
Request for Other Services (RFO) |
|
Any other issue/constraint/Challenge not falling into the above categories. |